Sizing guide

Quick answer: STP capacity (KLD) = number of users × water use per person per day (litres) × 0.8 ÷ 1,000. The 0.8 is the share of water that returns as sewage. Example: 500 residents × 135 litres × 0.8 = 54,000 litres a day, or 54 KLD. Then allow for peak flow and future phases before choosing the plant size.

Common packaged STP sizes, with who each one suits: 10 KLD, 50 KLD and 100 KLD.

✓ Users × litres × 0.8✓ NBC 2016 water use✓ CPHEEO peak factors
Packaged STP in chennai
HECS packaged STP in Chennai
135 L

Water per resident a day (NBC 2016)

0.8

Share of water that returns as sewage

2.0–3.0

CPHEEO peak factors

~300 mg/l

BOD of typical domestic sewage

Step 1: Count the users

Use the design population, not today’s occupancy: residents per flat (commonly 5 for planning), beds in hotels and hospitals, staff and visitors in offices, and students and staff in schools. Count each user group separately.

STP capacity calculation example: 100 flats x 5 residents x 135 litres x 0.8 = 54 KLD
Worked example: 100 flats come to about 54 KLD

Step 2: Find the water use per person

Building typeWater use (NBC 2016, Part 9)
Residences135 litres per person per day
Hotels with lodging180 litres per bed per day (more for luxury hotels)
Hospitals up to 100 beds340 litres per bed per day
Hospitals over 100 beds450 litres per bed per day
Hostels and boarding schools135 litres per person per day
Offices45 litres per person per day
Day schools45 litres per person per day
Restaurants70 litres per seat per day
Factories with bathrooms45 litres per person per day

Use your own metered or design water figures if you have them, and follow any figure your local authority or consultant specifies.

Step 3: Convert water to sewage

About 80% of the water supplied ends up as sewage, the design basis in the CPHEEO manual; the rest is used for gardening and cooking or evaporates. Multiply daily water use by 0.8. If garden or cooling water comes from a separate supply, leave it out.

Step 4: Allow for peak flow

Sewage does not arrive evenly: mornings and evenings bring peaks well above the average hourly flow. CPHEEO peak factors range from 2.0 for large populations to 3.0 for populations up to 20,000, so building-level plants sit at the higher end. A packaged STP handles this with an equalisation (collection) tank sized for the peaks, so the treatment stages see an even flow. Add a sensible margin and plan future phases as extra modules rather than oversizing on day one.

Step 5: Check the organic load

Capacity is not only volume. The biological stage is sized on the organic load: BOD load (kg a day) = flow (KLD) × BOD (mg/l) ÷ 1,000. Typical domestic sewage carries about 300 mg/l of BOD, so a 54 KLD flow brings about 16 kg of BOD a day. Kitchens, laundries and hospitals raise this, so share any effluent data you have with the designer.

Worked examples

ProjectCalculationSewageSuggested plant
Apartments, 100 flats100 × 5 × 135 × 0.854 KLD60 KLD
Hotel, 120 beds and 50 staff(120 × 180 + 50 × 45) × 0.8about 19 KLD20–25 KLD
Hospital, 200 beds200 × 450 × 0.872 KLD75–80 KLD, plus an ETP for lab and laundry effluent
Office or IT park, 2,000 staff2,000 × 45 × 0.872 KLD75–80 KLD
Day school, 1,500 students and staff1,500 × 45 × 0.854 KLD60 KLD

Common sizing mistakes

  • Sizing on today’s occupancy instead of the design population
  • Forgetting staff, visitors, kitchens or laundries
  • Ignoring peak flow, which overloads small plants in the morning
  • Oversizing on day one, which leaves the biology under-loaded; plan modules for later phases
  • Treating hospital lab and laundry effluent as sewage instead of sending it to an ETP
Residential packaged sewage treatment plant
Packaged STP installed above ground at a residential site

Get a first estimate in a minute

Use the HECS water consumption and sewage generation calculator for a first estimate, then see our packaged STP guide and STP cost guide. An HECS engineer confirms the final size from your site data.

FAQs

STP capacity calculation: FAQs

Can’t find your answer? Ask an HECS engineer. We reply within minutes.

Multiply the number of users by water use per person per day and by 0.8, then divide by 1,000 to get KLD. Allow for peak flow and future phases before choosing the size.

KLD = users × litres per person per day × 0.8 ÷ 1,000.

At 135 litres of water per person a day and 80% return, about 108 litres of sewage a day.

About 54 KLD at 5 residents per flat, so a 60 KLD plant is a sensible start.

Use beds × water per bed (340 litres up to 100 beds, 450 litres above 100 beds under NBC 2016) × 0.8, and send lab, OT and laundry effluent to an ETP.

The plant treats 100,000 litres of sewage a day, enough for roughly 900 residents at 135 litres per person.

Get your STP sized by an engineer

Send your building type, users or flats and city. We will confirm the capacity and quote the right packaged STP.

3 Replies to “STP Capacity Calculation: How to Size a Sewage Treatment Plant”

  1. […] Then size the plant with our STP capacity calculation guide. […]

  2. […] The 100 litres per worker is an assumption for the example; replace it with your camp’s figure. Use the capacity calculator and STP capacity calculation. […]

  3. […] Example: 100 flats × 5 residents × 135 litres × 0.8 = 54 KLD, so a 60 KLD plant is a sensible start. Use the capacity calculator, the packaged STP guide and STP capacity calculation. […]

Comments are closed.